Project Description

“Manufacturing facility for metal items”

Reconstruction and new building area 2000м²

 

The office building was completely remodelled, also new wings were added to the manufacturing building. New walls and isolation works were done on the roof and the facades of the metal building. Brick walls were reinforced to turn them into load bearing concrete walls using concrete under pressure to cover them. Also the slab of the second storey of the building was reinforced by making it thicker using self obturating concrete. The wooden roof construction of one of the sections was alos reinforced using metal beams and columns.

 

Investor: “Defence Capital Industry” LTD
Timeline: 01.09.2015 – 01.05.2016
Location: Sofia